Interstate 80 travel delays through Truckee anticipated for next four months
Submitted by paula on Fri, 08/05/2022 - 7:02pm
TRUCKEE – Travel delays are continuing through November on Interstate 80 (I-80) in Truckee for roadway construction activities.
Motorists are advised to expect typical delays of 15 to 20 minutes when traveling through the work zones on weekdays. However, delays of 25 to 30 minutes are common on Thursday afternoons due to increased weekend travel levels.
On I-80 eastbound, the #2 (right) lane will be closed around the clock from 8 p.m. Sunday, August 7 through 10 a.m. Friday, August 12 between Donner Pass Road/Cold Stream Road (Exit 184) and State Route 89 (SR-89) south (Exit 185). In addition, the SR-89 south eastbound on-ramp may be closed intermittently during the day Monday through Friday for paving work.
Motorists should also expect intermittent lane reductions in the SR-89 south roundabout for bore drilling work. Crews will be intermittently closing lanes as they work their way around the rounadbout.
Concrete and roadway widening work also continue on I-80 westbound between Central Truckee (Exit 186) and Donner Pass Road/Cold Stream Road (Exit 184) with alternating lane closures anticipated between 8 p.m. Sunday and 10 a.m. Friday for several weeks. The I-80 westbound off-ramp to Donner Pass Road/Cold Stream Road (Exit 184) may also be closed intermittently for maintenance work the weeks of August 8 and August 15.
The construction activities are part of a $30.6 million project to rehabilitate the existing concrete on I-80 in Truckee, install a westbound auxiliary lane from the SR-89 south on-ramp to the Donner Pass Road off-ramp, install eastbound acceleration lanes from the Donner Pass Road on-ramp and the SR-89 south on-ramp, improve drainage, and upgrade concrete walkways along ramps to meet current Americans with Disabilities Act (ADA) standards.
Teichert Construction of Rocklin is the prime contractor for the project, which is scheduled to be completed in fall 2022. The construction schedule is subject to change based on weather, equipment availability, lane closure restrictions during Hot August Nights or other unexpected events.
The department will issue construction updates on Twitter @CaltransDist3, on Facebook at CaltransDistrict3 and on the Caltrans District 3 website. For real-time traffic, click on Caltrans’ QuickMap quickmap.dot.ca.gov/ or download the QuickMap app from the App Store or Google Play.