lake tahoe road work

Lake Tahoe road work schedule for May 15-21, 2016

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by summer 2017.

Lake Tahoe road work schedule for April 3-9, 2016

LONG-TERM PROJECTS
State Route 89 (Placer County): Work is in winter suspension on a $70.1 million project from Tahoma to Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8.5-mile stretch of the highway. Completion is expected by spring 2017.

Lake Tahoe area roadwork for week of February 15-20

State Route 49 (El Dorado County) from the Coloma School House to Mt. Murphy Road: Motorists can expect one-way traffic from 8 a.m. to 5 p.m. Monday through Friday for utility work.

U.S. Highway 50 (El Dorado County) from Upper Truckee Road to Transit Way in South Lake Tahoe: Eastbound and westbound motorists can expect alternating lane closures from 9 a.m. to 5 p.m. Wednesday through Friday for survey work.

Lake Tahoe road work schedule for December 7 - 12

Work on all Lake Tahoe basin projects is either suspended for the season or completed. Here is an update on all projects. There is still road work being done on a stretch of Highway 50 in El Dorado Hills:

Lake Tahoe road work schedule for November 29 - December 4

There is no road work scheduled for the South Shore this week. Here are the current projects around the lake:

Interstate 80 (Placer County) from Brace Road to Magra Road: Work continues on a $36 million project to increase the vertical clearance of nine bridge structures in south Placer County to 16 feet, 6 inches. The vertical clearance will be increased on seven structures by lifting the existing bridge deck and the other two will have the roadway below dug down. More information on the project is available at www.raise80.com

Lake Tahoe road work schedule for November 22-28

Because of the Thanksgiving holiday, most lane closures will be restricted from 6 a.m. Wednesday, November 25 until 8 p.m. Sunday, November 29.

LONG-TERM PROJECTS

Lake Tahoe road work schedule for November 15-21

LONG-TERM PROJECTS

State Route 89 (Placer County): Work is in winter suspension on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 8 - 14

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 1 - 7

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 25 - 31

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 18 - 24, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 11 - 17, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 5-10, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 27 - October 3

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 20 - 26, 2015

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 13 - 19, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 6 - September 12

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 30 - September 5

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 23 - August 29

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 16 - 22

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 9 - 15

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 2 - 8

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 27 - August 1

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 20 - July 25

Long Term Projects

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 12-18

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for June 29 - July 2

Due to the increase of travelers expected in the Lake Tahoe basin, all road work projects will end for the week on Thursday, July 2.

On the South Shore:

Lake Tahoe road work schedule for June 21 - June 27

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 2nd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures from 7 p.m. to 7 a.m. Monday through Friday for gas line relocation work. Eastbound motorists can also expect the right shoulder closed at the same location from 7 a.m. to 7 p.m. for trenching.

Lake Tahoe road work schedule for June 14 - June 20

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 3rd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures around the clock from 7 a.m. Monday to 7 a.m. Friday for gas line relocation work.

Lake Tahoe road work schedule for June 7 - June 12

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 2nd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures from 5 p.m. to 11 a.m. Monday through Friday for gas line relocation work.

Lake Tahoe road work schedule for May 26 - May 29

Here is the Lake Tahoe area road report for the week of May 26-29, 2015:

State Route 89 (El Dorado/Placer County) from Wilson Avenue to Elm Street: Motorists can expect one-way traffic control from 7 a.m. to 5:30 p.m. Wednesday and Thursday and 7 a.m. to noon Friday for bump grinding. Motorists can also expect one-way traffic from McKinney Drive to Madden Creek around the clock from 8 p.m. Tuesday to noon Friday for roadway excavation.

Syndicate content