Lake Tahoe road work schedule for September 27 - October 3

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Sept. 27-Oct. 2 - State Route 89 (Placer County) from McKinney Drive North to South Street and Grimsel Pass Road to St. Michael’s Court: Motorists can expect one-way traffic control around the clock from 10 p.m. Sunday to noon Friday for drainage and concrete work.

State Route 89 (El Dorado County): Work continues on a $20 million water-quality project from 0.1 mile north of the Eagle Falls Sidehill Viaduct No. 5 in Emerald Bay to the Meeks Creek Bridge in Meeks Bay. This project is adding new drainage features, curb and gutter in some locations, and resurfacing a nearly 7-mile stretch of the highway. The project will be completed this fall.

Sept. 28-Oct. 2 - State Route 89 (El Dorado County) from 3 Ring Road to 1 Ring Road: Motorists can expect one-way traffic control from 7 a.m. to 5 p.m. Monday through Thursday and 6 a.m. to 11 a.m. Friday for paving and 6 p.m. to 6 a.m. Monday through Friday for guardrail work.

State Route 89 (El Dorado County): Work continues on an $8 million project from Meeks Creek to Wilson Avenue in Tahoma, installing curb and gutter and drainage systems to collect and treat stormwater. The highway will also be resurfaced. The project will be completed this fall.

Sept. 27-Oct. 2 - State Route 89 (El Dorado County) from Meeks Creek to Wilson Avenue: Motorists can expect one-way traffic control around the clock from 7 p.m. Sunday to 11 a.m. Friday for pavement work.

State Route 89 (El Dorado County): Work continues on a $25 million project from the "Y" junction with U.S. Highway 50 in South Lake Tahoe to Cascade Road, north of Camp Richardson. Curb, gutter and sidewalks will be added in the 1.1-mile four-lane section, and the highway will be widened in the two-lane section to Visitor Center Road to provide 4-foot paved shoulders on each side. Drainage systems are also being built and the roadway will be resurfaced. Completion is expected by spring 2017.

Sept. 27-Oct. 2 - State Route 89 (El Dorado County) from the “Y” intersection to 13th Street and from Spring Creek Road to Cascade Road: Motorists can expect alternating lane closures in the four-lane section and one-way traffic control in the two-lane section around the clock from 10 p.m. Sunday to 11 a.m. Friday for curb, gutter and sidewalk work, and drainage work.

State Route 28 (Placer County): Work continues on Placer County’s $50 million Kings Beach Commercial Core Improvement Project from State Route 267 to Chipmunk Street. The project is installing curb and gutter, sidewalks, roundabouts, lighting and drainage systems to enhance pedestrian and bicycle mobility, improve safety and provide water-quality improvements. Completion is expected this fall. For more information on the KBCCIP, go to: http://kingsbeachcore.info/

Sept. 27-Oct. 2 - State Route 28 (Placer County) from the junction with State Route 267 to Bear/Brook Street: Eastbound motorists should expect shoulder closures from 7 a.m. to 5:30 p.m. Monday through Friday for curb, gutter and sidewalk work.

State Route 267 (Placer County): Work continues on a $5.2 million project to grind, pave and make drainage improvements to a nearly seven-mile stretch of State Route 267 from just north of Schaffer Mill Road to Brockway Summit. Completion is expected by the end of September.

Sept. 27-Oct. 2 - State Route 267 (Placer County) from the Nevada County line to Carnelian Bay Avenue: Motorists can expect one-way traffic control from 9 p.m. Sunday to 6 a.m. Monday and 6 p.m. to 6 a.m. Monday through Friday for pavement work.

U.S. Highway 50 (El Dorado County): Work continues on a $57 million project by El Dorado County to construct a new overcrossing over U.S. Highway 50, new on- and off-ramps with signalized intersections, and new bicycle and pedestrian facilities at Silva Valley Parkway in El Dorado Hills. Completion is expected in 2016. For more information on this project, go to http://www.edcgov.us/SIlvaValley.aspx

Sept. 28-Oct. 3 - U.S. Highway 50 (El Dorado County) from Latrobe Road/El Dorado Hills Boulevard to Bass Lake Road: Westbound motorists can expect alternating lane closures from 8 p.m. Monday to 5 a.m. Tuesday for median barrier work. Eastbound motorists can the #3 and #4 lanes closed from 9 p.m. to 5 a.m. Wednesday through Friday and 9 p.m. Friday to 8 a.m. Saturday for paving. The eastbound Latrobe Road/El Dorado Hills on-ramp will be closed from 9 p.m. Thursday to 5 a.m. Friday and 10 p.m. Friday to 7 a.m. Saturday for paving.

State Route 49 (El Dorado County): Work continues on an $8.4 million project to repave an 11-mile section of State Route 49 from Cool to Coloma. Most of the paving will use cold-in-place recycling in which the existing pavement is ground up and reused and then an asphalt overlay is placed on top of it. Rocks have also been added to some shoulder areas for erosion control and guard rail replaced. Completion is expected this fall.

Sept. 28-Oct. 2 - State Route 49 (El Dorado County) from Lotus Road to Ranch Creek Circle: Motorists can expect one-way traffic control at various locations around the clock from 7 p.m. to 6 a.m. Sunday through Saturday for pavement and drainage work.

SHORT-TERM PROJECTS

U.S. Highway 50 (El Dorado County) from the Upper Truckee River Bridge to Tulare Avenue/Al Tahoe Boulevard in South Lake Tahoe: Eastbound and westbound motorists can expect the #1 lane closed around the clock from 8 p.m. Sunday to 10 a.m. Friday for gas line relocation work.

State Route 89 (Placer County) from Tan Tavern Road to Mackinaw Road in Tahoe City: Northbound motorists can expect the right shoulder closed from 7 a.m. to 7 p.m. Monday and Tuesday for utility work.

State Route 89 (Placer County) at Alpine Meadows Road: Motorists can expect one-way traffic control from 7 a.m. to 5 p.m. Monday through Friday for electrical work.

State Route 89 (Placer County) between Squaw Valley Road and West River Street: Motorists can expect one-way traffic control at various locations from 7 a.m. to 5 p.m. Monday through Thursday for shoulder work.

State Route 193 (El Dorado County) from Meadow Brook Road to Spanish Flat Road: Motorists can expect one-way traffic control from 8 a.m. to 3 p.m. Monday through Friday for tree work.