NDOT SR431-28 project at Lake Tahoe scheduled to start May 1
Submitted by paula on Sun, 04/23/2023 - 8:57am
Marlette Creek: IGVID relocating utilities
INCLINE VILLAGE, Nev. - The third construction season of State Route 431 and 28 improvements is scheduled to begin Monday, May 1, weather dependent. The May schedule includes:
SR28- Installing ITS conduit through Incline Village (Northwood Blvd to Ponderosa Ranch Rd)
SR28 - Guardrail, curb, gutter, ADA ramp installation through Crystal Bay
Marlette Creek: IGVID relocating utilities
Traffic Control
For the first few weeks of the season, normal working hours are Sundays at 8 p.m.- Fridays at 7 p.m. All work is weather permitting and excludes major holidays. During the summer work will end at noon on Fridays.
Drivers can expect multiple work zones and up to 30-minute delays with single-lane, flagger-controlled closures.
Commercial vehicles with air brakes (26,000 pounds or greater) are prohibited from traveling westbound over Mt. Rose Summit from Mt. Rose Ski Resort to Incline Village. Trucks will be allowed to travel eastbound from Incline Village to Reno. Nevada Highway Patrol (NHP) officers will be monitoring.
Stay informed of traffic and roadwork on Tahoe-area highway via text and Twitter:
Text the word "Incline" to 775-242-9168 to sign up for project-related construction updates. You’ll receive text alerts for major lane and other closures right to your phone.
Also, follow @nevadadotreno on Twitter for highway conditions and updates for your northwestern Nevada commutes and travels.
Ride! Let others drive.
NDOT is encouraging Lake Tahoe visitors to find a ride versus drive to help reduce the amount of traffic within the basin. Tahoe Transportation District's East Shore Express, and Tahoe Truckee Area Regional Transportation’s Mainline / TART Connect, are some local and cost-effective solutions to riding around Tahoe. Learn more about these services and others by visiting: https://www.inclinehighways.com/resources.
The Nevada Department of Transportation and Q&D Construction's SR 431-28 Tahoe Project is a multi-year highway improvement project that will revitalize and enhance the existing roadways and utility/drainage systems helping preserve pavement and protect Lake Tahoe.
Drivers can expect reduced speeds through the work zone and up to 30-minute delays. Construction operations are weather dependent and subject to change.