Lake Tahoe area roadwork June 25 - July 1

EMERGENCY PROJECTS

State Route 89 (El Dorado County) from South Upper Truckee Road to Luther Pass: Motorists can expect one-way traffic control at various locations from 6:30 a.m. to 5 p.m. Monday through Thursday for dead tree removal work.

U.S. Highway 50 (El Dorado County): The highway is reduced to one lane in each direction at Bridal Veil Falls for slope repair work.

U.S. Highway 50 (El Dorado County) at Alder Creek Road: Motorists can expect intermittent one-way traffic control from 6 a.m. to 6 p.m. Monday through Thursday and 6 a.m. to noon Friday for mudslide removal work.

State Route 193 (El Dorado County): Motorists can expect signalized one-way traffic control about 1 mile north of the junction with State Route 49 in Placerville around the clock for slope repair work.

LONG-TERM PROJECTS
State Route 49 (El Dorado County): Work continues on a $22 million project to replace the South Fork American River Bridge in Coloma-Lotus. This project will make seismic improvements, widen the bridge to allow for 8-foot shoulders and sidewalks, and also make roadway improvements to State Route 49 on either side of the bridge. Completion is expected in fall 2018. June 26-30 - State Route 49 (El Dorado County) at the South Fork American River Bridge: Motorists can expect one-way traffic control from 6 a.m. to 6 p.m. Monday through Friday for water line relocation and bridge work.

U.S. Highway 50 (El Dorado County): Work continues on a $57 million project from the “Y” intersection with State Route 89 to the Trout Creek Bridge in South Lake Tahoe. This project is building new drainage systems to collect and treat stormwater runoff, rebuilding curb, gutter and sidewalks, widening the highway to allow for bike lanes and resurfacing the roadway. Completion is expected in fall 2019. June 26-30 - U.S. Highway 50 (El Dorado County) from Dunlap Drive to Tahoe Keys Boulevard: Westbound motorists can expect the #2 lane closed around the clock from midnight Monday to 8 a.m. Friday for curb, gutter and sidewalk work, and drainage work. The two-way left turn lane will be used as a travel lane during daytime work and left turns will be restricted.

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8.5-mile stretch of the highway. Completion is expected by the end of July.June
25-30 -
State Route 89 (Placer County) from Ward Creek to Spruce Avenue: Motorists can expect one-way traffic control from 10 p.m. Sunday to 10 a.m. Monday and 7 p.m. to 10 a.m. Monday through Friday for utility work. Motorists also can expect one-way traffic control from Fawn Street to Cherry Street from 10 p.m. to 10 a.m. Sunday through Thursday for drainage work and from Fawn Street to Trout Street from 10 a.m. to 6 p.m. Monday through Thursday for electrical work.

State Route 89 (Placer County): Work continues on a $35 million project in Tahoe City to build a new Truckee River bridge east of the Caltrans Maintenance Yard with roundabouts on either end of the realignment, replace the existing Truckee River (Fanny) Bridge, construct a roundabout at the “Wye” intersection and make complete street enhancements to the portion of State Route 89/West Lake Boulevard that will become a local road after project completion, which is expected in 2018. For more information on this project, visit: www.fannybridge.org June 26-30 - State Route 89 (Placer County) from the Tahoe City Transit Center to the Caltrans Maintenance Yard: Motorists should expect one-way traffic control at various locations from 10 p.m. Sunday to 9 a.m. Monday and from 8 p.m. to 9 a.m. Monday through Friday for curb, gutter and sidewalk work and utility work.

SHORT-TERM PROJECTS

U.S. Highway 50 (El Dorado County) from Upper Truckee Road to Cingu Street in Meyers: Motorists can expect one-way traffic control from 7 p.m. Monday to 9 a.m. Tuesday for bridge work.

U.S. Highway 50 (El Dorado County) from Ski Run Boulevard to Fairway Avenue in South Lake Tahoe: Westbound motorists can expect the #2 lane closed from 7 a.m. to 5 p.m. Monday through Thursday for curb, gutter and sidewalk work.

State Route 28 (Placer County) from Carnelian Bay Avenue to Agate Road: Motorists can expect one-way traffic control from 6 a.m. to 8 p.m. Monday and Tuesday for utility work.

State Route 89 (El Dorado County) at the Sidehill Viaduct at Emerald Bay: Motorists can expect one-way traffic control from 7 p.m. to 9 a.m. Monday through Friday for bridge deck work.

State Route 89 (Placer/Nevada County) from Squaw Valley Road to Donner Pass Road in Truckee: Motorists can expect one-way traffic control at various locations from 6 p.m. to 6 a.m. Monday through Friday for pavement repairs.

State Route 267 (Placer County) from Stewart Way to the junction with State Route 28 in Kings Beach: Motorists can expect one-way traffic control at various locations from 7 p.m. to 5 a.m. Sunday through Wednesday for pavement repairs.