Kingsbury Grade project completed a year ahead of schedule
Submitted by paula on Fri, 11/21/2014 - 10:45pm
The $15 million Kingsbury Grade repaving and enhancement project finished one year ahead of schedule, according to a Nevada Department of Transportation announcement Thursday.
Major work on the project was expected to be completed during the Summer, 2015, but instead NDOT announced that it was substantially completed this week.
Since the project’s start in May, nearly four miles of roadway were reconstructed, including excavation of approximately 24,000 cubic yards of old road and placement of 24,000 tons of new asphalt. More than 6,000 linear feet of storm drain pipe, 3,300 linear feet of sidewalk and 8,700 linear feet of curb and gutter were also installed as one part of the project’s safety, accessibility and drainage improvements.
To help expedite project work, two closures to through traffic took place: one in May and one in September/early October. By limiting the amount of traffic on Kingsbury Grade, crews were able to increase the amount of work they were able to complete.
“These traffic closures helped us complete work in half the time we would otherwise be able to,” NDOT Project Manager Pedro Rodriguez explained. “We know that a traffic closure like this impacts drivers and residents, and we want to thank each and every Kingsbury Grade motorist, resident and business, and the entire Tahoe and Carson Valley communities, for their understanding. The professional, expeditious work of the contractor, Q&D Construction, and the understanding of the community truly led this to be a successful project. Thanks to the community’s understanding, we have been able to complete this project ahead of schedule!”
The project also utilized the Construction Manager at Risk process, which brings project designers and contractors together from the very start of the project with the goal of completing it more quickly, efficiently and cost effectively.
The project reconstructed pavement on portions of Kingsbury Grade to a 13-inch depth, which will help prevent continuing pavement deterioration from natural springs below the roadway. The project also made drainage, safety, curb and gutter, sidewalk, lighting and other improvements.
- 2015
- asphalt
- business
- carson
- carson valley
- closure
- closures
- community
- construction
- contractor
- contractors
- department
- department of transportation
- Help!
- improvements
- kingsbury
- kingsbury grade
- Lake Tahoe
- LED
- natural
- ndot
- Nevada
- nevada department of
- nevada department of transportation
- News
- road
- roadway
- safety
- south lake tahoe
- state route 207
- storm
- storm drain
- summer
- Tahoe
- Traffic
- transportation
- work
Related Stories
- Motorists preparing for month long Kingsbury Grade Closure
- Kingsbury Grade project wins TRPA "Best in Basin" Award
- Kingsbury Grade is reopening to through traffic on Tuesday
- Kingsbury Grade Closing to Through Traffic in May, September and October
- Kingsbury Grade Closes to Valley Traffic Thursday; Bus Ridership to be Monitored
- SR28 south of Incline Village to close overnight Dec. 11-13
- Kingsbury Grade closed indefinitely after rocks and dirt slide onto road
- NDOT begins long list of repairs in Nevada after storm damage