Lake Tahoe, Sierra and El Dorado County roadwork November 22 - 28
Submitted by paula on Sat, 11/21/2020 - 8:50am
SOUTH LAKE TAHOE, Calif. - The following is a list of the long term and short term projects the California Department of Transportation (Caltrans) has scheduled for the week around Lake Tahoe, in the Sierra and El Dorado County. At this time there is no work scheduled for the South Lake Tahoe area.
Most traffic-interfering work will be restricted from 6 a.m. Wednesday, Nov. 25 until 10 p.m. Monday, Nov. 30 due to the Thanksgiving holiday.
LONG-TERM PROJECTS
U.S. Highway 50 (El Dorado County): Work continues on a $55.4 million safety project in the Camino area to replace the existing concrete median barrier and fill in the gaps in the barrier, build an undercrossing, a wildlife crossing, make local road improvements and replace culverts. The project is expected to be completed in late 2022. No traffic-interfering work is scheduled on the highway.
U.S. Highway 50 (El Dorado County): Work continues on an $11.5 million project to replace the U.S. Highway 50 Sawmill (Ridgeway Drive) Undercrossing in Pollock Pines to address the aging bridge deck, improve sight distance, bring the bridge railings up to current design standards and make improvements to Ridgeway Drive, including curb, gutter and sidewalk work. The project also includes adding overhead lights to the Sly Park Road on- and off-ramps. Completion is expected by June 2021. Highway 50 is reduced to one lane in each direction through the construction zone.
Nov. 24-25 - Ridgeway Drive (El Dorado County): Motorists can expect one-way traffic control through the undercrossing from 6:30 a.m. to 3 p.m. Tuesday and 6:30 a.m. to noon Wednesday for paving work.
U.S. Highway 50 (El Dorado County): Work continues on a $19 million project to stabilize the westbound section of the highway in Fresh Pond by building a 428-foot-long retaining wall, concrete barrier and repaving the highway. This location on US 50 has a history of surface cracking and sinking. Completion is expected by spring 2022. Highway 50 is reduced to one lane in each direction through the construction zone.
Nov. 24-25 - U.S. Highway 50 (El Dorado County): Eastbound and westbound motorists can expect alternating lane closures within in the project limits from 9 p.m. Tuesday to 7 a.m. Wednesday for striping work.
State Route 49 (Placer County) from the I-80/SR 49 interchange to Dry Creek Road: Construction began June 17, 2019 on a $42.4 million project in Auburn. The project will rehabilitate existing pavement and drainage, improve operational features and upgrade pedestrian and bicycle facilities.
November 22 – November 25 - State Route 49 (Placer County) from the Interstate 80 junction to Dry Creek Road: Motorists may expect intermittent lane and shoulder closures from 6 p.m. to 6 a.m. Sunday through Wednesday morning for electrical and drainage and electrical work, grinding and paving, and curb and sidewalk work.
State Route 49 (Nevada County) from Woodridge Drive to Linton Lane: Construction began July 27 on a $3.8 million safety improvement project on State Route 49 near Wolf Road and Combie Road. Caltrans is constructing a northbound and southbound acceleration lane and adding other safety and operational improvement elements. Work will primarily be performed along shoulders behind concrete barriers, with minimal impacts to traffic. Major work on the project is complete with final electrical work anticipated in December or January.
State Route 49 (Nevada County) from Auburn Road to Alta Sierra Drive: Vegetation work is beginning for a $4.3 million safety improvement project on State Route 49 near Round Valley Road and Quail Creek Drive. Caltrans is constructing a two-way left turn lane with an increased 8-foot-wide southbound shoulder. Major construction work is expected in spring 2021. This project is currently in winter suspension.
State Route 49 (Sierra County) from Yuba Pass Road to Vista Point: Construction began August 10 on a $3.7 million project to widen shoulders and improve the super elevation of the highway to reduce collisions. Work has been completed on this project.
Interstate 80 (Placer/Nevada Counties) between Alta and Floriston: A $6.6 million structure maintenance project will replace polyester concrete overlays and joint seals on 11 bridges. The project will extend the life of the bridge decks by sealing them off to moisture and fix rutting in the concrete overlays caused by heavy freight and vehicle travel.
November 23 – November 24 -
-Interstate 80 (Placer County) at Alta: Motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
-Interstate 80 (Placer County) at Blue Canyon: Eastbound motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
-Interstate 80 (Nevada County) at Donner Pass Road near the chain installation area: Motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work- .
-Interstate 80 (Nevada County) from the Interstate 80/State Route 89 separation to the Interstate 80/State Route 89/State Route 267 separation: Motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
-Interstate 80 (Nevada County) from the Union Mills Bridge Overcrossing to the Hinton Road Overcrossing: Motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
-Interstate 80 (Nevada County) at Floriston: Motorists may expect intermittent lane and shoulder closures from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
Interstate 80 (Nevada County) from Farad to the Acid Flat Bridge: An $12.9 million Farad Ditch Slope Stabilization project will restore the Farad Ditch by extending the collection area. Construction will also include regrading of the slope by means of roadway excavation, rock excavation, and controlled blasting.
November 23 – November 24 - Interstate 80 (Nevada County) from Farad to the Acid Flat Bridge: Westbound motorists may expect intermittent lane closure from 6 a.m. to 7 p.m. Monday through Tuesday for roadway excavation.
State Route 174 (Nevada County) from Maple Way to You Bet Road: A $27.1 million safety improvement project will realign several curves, widen shoulders, add a southbound left turn pocket at Greenhorn Access Road and improve the clear recovery zone, allowing errant vehicles to regain control. No traffic-interfering work is scheduled this week.
SHORT-TERM PROJECTS
State Route 28 (Placer County) from Ridgewood Road to Carnelian Bay Road Motorists can expect one-way traffic control from 7 a.m. to 5 p.m. Monday and Tuesday for utility work.
State Route 49 (El Dorado County) at Baker Road: Motorists can expect one-way traffic control from 8 a.m. to 5 p.m. Monday utility work.
State Route 193 (El Dorado County) from Traverse Creek Road to Spanish Flat Road: Motorists can expect one-way traffic control from 8:30 a.m. to 5 p.m. Monday and Tuesday for tree work.
State Route 49 (Placer County) from Fresh Air Lane to Hummingbird Lane: Motorists may expect intermittent lane and shoulder closures from 7 p.m. to 6 a.m. Monday through Wednesday morning for utility work.
State Route 49 (Yuba/Sierra Counties) from Marysville Road in Yuba County to Yuba Pass Road in Sierra County: Motorists may expect intermittent, one-way traffic control from 8:15 a.m. to 3:15 p.m. Monday through Wednesday for miscellaneous work.
State Route 49 (Sierra County) at Ladies Canyon: Motorists may expect one-way traffic control and shoulder closures from 6 a.m. to 6 p.m. Monday through Tuesday for bridge work.
State Route 65 (Placer County) from Sunset Boulevard to Levee Road: Motorists may expect intermittent right shoulder closures from 9 a.m. to 2:30 p.m. Monday for a sweeping operation.
Interstate 80 (Placer County) at Riverside Avenue/Auburn Boulevard: Westbound motorists may expect full ramp closures from 9 p.m. Sunday through 5 a.m. Monday, and 10 p.m. to 5 a.m. Monday through Wednesday morning for electrical work.
Interstate 80 (Placer County) at the State Route 174 junction: Motorists may expect lane and shoulder closures on the local cross street from 9 a.m. to 5 p.m. Monday through Tuesday for drainage work.
Interstate 80 (Placer County) from the State Route 174 junction to Canyon Way: Eastbound motorists may expect right shoulder closures from 9 a.m. to 5 p.m. Monday through Tuesday for drainage work.
Interstate 80 (Nevada County) from Yuba Gap to the Interstate 80/State Route 20 junction: Motorists may expect intermittent lane closures from 7 a.m. to 6 p.m. Monday through Tuesday for bridge work.
State Route 89 (Nevada County) at Donner Pass Road: Motorists may expect lane and shoulder restrictions from 6 a.m. to 8 p.m. Monday through Tuesday for bridge work.
State Route 89 (Sierra County) from Old Truckee Road to the State Route 49 junction: Motorists may expect intermittent one-way traffic control and shoulder closures from 7 a.m. to 5 p.m. Wednesday for tree removal.
State Route 193 (Placer County) at the Newcastle Tunnel: Motorists may expect lane and shoulder closures from 8:30 a.m. to 5 p.m. Tuesday for tree removal.
State Route 267 (Nevada County) from Schaffer Mill Road/Truckee Airport Road to Glenshire Drive: Motorists may expect intermittent lane and shoulder closures from 7 a.m. to 5 p.m. Monday through Tuesday for electrical work.
- 1
- 2019
- 2021
- aging
- airport
- auburn
- baker
- bicycle
- blue
- bridges
- building
- california
- california department of transportation
- Caltrans
- camino
- carnelian bay
- closure
- closures
- construction
- county
- department
- department of transportation
- design
- donner
- donner pass
- el dorado
- el dorado county
- el dorado county
- highway
- highway 50
- history
- holiday
- improvements
- lake
- Lake Tahoe
- life
- local
- Nevada
- nevada county
- News
- park
- pedestrian
- placer county
- pollock pines
- projects
- Recovery
- restrictions
- riverside
- road
- road construction
- roadway
- roadwork
- route 28
- safety
- Shoulders
- sierra
- south lake tahoe
- spanish
- spring
- state
- state route 28
- state route 89
- Tahoe
- tahoe sierra
- thanksgiving
- Traffic
- transportation
- travel
- tree
- tree removal
- Truckee
- tunnel
- us 50
- vehicle
- wildlife
- winter
- work
Related Stories
- Lake Tahoe, Sierra and El Dorado County roadwork November 30 - December 5
- Lake Tahoe, Sierra and El Dorado County roadwork November 1 - 7
- Lake Tahoe, Sierra and El Dorado County roadwork October 25 - 31
- Lake Tahoe, Sierra and El Dorado County roadwork December 20 - 26
- Lake Tahoe, Sierra and El Dorado County roadwork November 15-21
- Lake Tahoe, Sierra and El Dorado County roadwork November 8 - 14
- Lake Tahoe, Sierra and El Dorado County roadwork October 18-24
- Lake Tahoe, Sierra and El Dorado County roadwork October 11-17